26. Using the information below, draw an AOA network. Find the path with the longest expected duration, and use it to compute the number of days you would be 95 percent sure the project would be completed. Calculate the slack, earliest start, and latest start times for each activity and show in table form. Does any path come close to causing a problem in determining the probability of project completion based on just using the path with the longest expected duration?