- Cp (Process Capability Index) is calculated using the formula: Cp = (USL - LSL) / (6 * standard deviation) - Cpk (Process Capability Index with respect to the mean) is calculated using the formula: Cpk = min((USL - mean) / (3 * standard deviation), (mean - LSL) Show more…
Show all steps
Your feedback will help us improve your experience
Sri K and 92 other Algebra educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Key Concepts
Recommended Videos
Sri K.
Compute the Cpk measure of process capability for the following machine and interpret the findings. What value would you have obtained with the Cp measure? Machine data: USL = 100 LSL = 70 Process mean = 80
Banhishikha S.
What can be concluded when Cp equals Cpk? A The process capability is greater than 1.33 B The process is in control and capable C The process mean is centered between the upper and lower specifications D The specification limits are too narrow E There is very little process variation