00:01
So it says a time study was conducted on a job that contains four elements.
00:05
The observed times in performance ratings for six cycles are shown in the following table.
00:11
So it says for a, determine the average cycle time for each element.
00:14
Round your answers to three decimal places.
00:17
So i added up the first element and i got 2 .69 and then divided by 6.
00:25
And i got 0 .4483 repeating.
00:31
So rounded to three decimal places, 0 .448.
00:38
Then for two, i added them up.
00:41
I got one and then divided by six.
00:44
I got 1 .508.
00:46
For element three, added them up, divided by six, and i got 0 .833.
00:52
For four, i added those numbers up.
00:56
And divided by six, and i got 1 .152.
01:00
One, one point one five two.
01:03
For whatever reason, it doesn't let me right over here.
01:07
Okay, it's just very stubborn.
01:15
Okay, there we go.
01:16
All right, for b, find the normal time for each element...