An engineering firm measures its output in standard service hours (SSH) per unit, which is a function of the skill levels of its engineers (skill levels range from an engineering intern to an engineering scientist.The variable cost is $60 per SSH and the fixed cost is $2,000,000 per year. The firm charges $100 for each service per hour.Assume the maximum hours the firm operates (that is the output is 170,000 per year.
a) Compute the break-even point in SSH.
bAt what percentage does the break-even occur as compared to the maximum hours the firm operates?
c)What is the percentage reduction in break-even point if the fixed cost can be reduced by 20%?
d) Does the break-even point increase or decrease if the charges per service is increased by 10%?
e) What is your recommendation? Should the firm reduce the fixed cost or increase the price?