00:01
Okay, so here fixed cost is 108, and we can derive the variable cost and total cost from these.
00:08
So the variable cost, excuse me, total cost is equal to fixed cost plus the variable cost.
00:16
So we can go from the first few entry of the total cost.
00:23
So at output 0, this is 108, and output 1 .1, this is 1 .8.
00:34
Is equal to 108 plus 12.
00:40
Let me do this vertically here.
00:43
0108.
00:44
So this is the output and total cost.
00:52
0, we have 108 and 1.
00:56
We have a variable cost of 12 here, so 1 .08 plus 12, 120.
01:03
2.
01:04
We have a variable cost of 12 here, so 1 .0 .2.
01:05
We have a variable cost of 48, which gives 150.
01:17
At output 3, this is, oh, you already have this one, so you don't need this one here.
01:31
And all the way up to output 9, you have the variable cost of 972.
01:43
So you obtain a 1 .80, and at output 10, you have the variable cost of a...
01:57
1200, so 1 -2, excuse me, 1 -308.
02:08
Okay, now you can do the variable cost.
02:13
So from this formula, you can see that the variable cost is equal to total cost minus the fixed cost...