“In 24 days, 15 workers have completed 1/4 of a job. How many days will it take another crew of 30 workers who are three times as skilled to finish the job?”
Added by Myon M.
Step 1
Since they completed 1/4 of the job in 24 days, it would take them 24 * 4 = 96 days to finish the whole job. Show more…
Show all steps
Your feedback will help us improve your experience
Jacob Fry and 58 other Finite Mathematics and Calculus with Applications educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Recommended Videos
Sri K.
10 workers can finish the job in 15 days. For the first 5 days, only 6 workers worked on the job. Then for the next 3 days 2 more workers joined them. To finish the job, 4 more workers joined them. After how many days was the whole job done?
Maegan H.
Amit and Ananthu can do a work in 15 days and 25 days respectively. Amit started the work and left after 3 days. Ananthu took over and completed the work. In how many days was the total work completed? *
Victor S.
Recommended Textbooks
Finite Mathematics and Calculus with Applications
Understanding Our Universe
Further Pure Mathematics
Transcript
Watch the video solution with this free unlock.
EMAIL
PASSWORD