In a safety stock problem where both demand and lead time are variable, demand averages 100 units per day with a daily standard deviation of 15, and lead time averages 5 days with a standard deviation of 1 day. What is the ROP? Service level is 97.5%.
15 units
154 units
500 units
673 units
707 units