Prepare the Gantt chart using any diagram tool. Give the total duration time of the project.
Task T1 T2 T3 T4 T5 T6 T7 T8 T9 T10 T11 T12
Duration (days) 8 15 13 10 15 5 22 25 18 15 7 12
Dependencies
T1 T2
T3, T4 T1, T2, T3 T1 T4, T6 T3, T6 T5, T7 T9, T10 T11