Task No.
Description
Duration (Days)
Predecessor Tasks
1
Develop Plan
2
-
2
Assign Tasks
3
1
3
Obtain Hardware
4
2
4
Programming
17
3
5
Install Hardware
70
4,5
6
Program Test
10
5
7
Write User Manual
30
6
8
Convert Files
25
7,8
9
System Test
20
8
10
User Training
25
9,10
11
User Test
20
10