Spolns Question 5: Use the following information in a table about the activities of an HR Information System project of ABC Company LLC and solve the given question.
Dependencies/Task Duration Task Activities Predecessors (Days)
A1 - 6
A2 - 4
A3 A2 2
A4 A2 4
A5 A2, A3 7
A6 A4, A5 7
A7 A6 -