Suppose you have three independent projects - A, B, and C. Assume that the hurdle rate is 12% for all three projects. Their NPVs and IRRs are shown in the table below.
Project A GHS20,000 20%
Project B GHS21,400 32%
Project C GHS23,000 18%
Required: Assuming the projects are mutually exclusive, choose the most economically feasible project.