T3. 3c Calculate the achieved availability for equipment, knowing the following related data:
i. \( \quad M \overline{c t}=0.93 \mathrm{hr} \)
ii. \( \quad M T B M u=17 \mathrm{hrs} \)
iii. \( \quad M \overline{p t}=4.02 \mathrm{hrs} \)
iv. \( M \overline{T B M s}=21,980 \mathrm{hrs} \)
N.B. \( \overline{M T B M} u= \) Mean Time Between Maintenance (Unscheduled)
MTBM \( s= \) Mean Time Between Maintenance (Scheduled)
Use Excel and attach the file as an embedded file in a Word document/ upload file in Moodle with your analysis.
Is \( 95.00 \% \) achieved and what improvements are recommended to keep at its equipment availability rate?
Comment on what measure is used for analysing availability in your workplace or the workplace you have worked in the past or in your work experience/ maintenance project.