00:01
And this question, you look at a 4g shop of a small company, right? so it has, so it's basically about a forge shop, right? so this has 20, this shop has 204g prices, right? so i call this n, so they got 20, n equals 20 in prices.
00:24
You know, it takes about three hours to production, to put, it takes up about three hours to set up the, to set up production for each box, right? so it takes three hours for setting up the production with batch.
00:44
And a standard time for each part in a batch is 45 seconds.
00:50
And it takes the how many parts in a branch, so that 600 parts.
00:58
So altogether, the time takes to produce to, to, to, to, process one batch is 600 times 45 seconds, right? that's for one batch.
01:11
So let me call this time equals t.
01:15
This time equals t.
01:17
And you can put them, of course, into hours, three hours plus 45, that's 600 times.
01:25
So how many minutes? it's a three quarter minute, right? at one minute, 16 hours, right? so this is hours, right? so altogether, you'll find, is to be taken up this, you get 10, 30 over four, right? so that's three hours plus 30 over four hours, right? so that is the time to deal with one batch, right? so if you look at one month and it always work every day and 21 days per month, so how many parts can be produced, right? well, we just need to look at the, how many parts could be produced.
02:14
So you have eight hours a day and you have 21 days...