60% of projects are done on time each case, what is the probability out of 6 projects, 4 will be completed on time?
Added by Brandon M.
Step 1
We have a binomial distribution where: - The number of trials (n) is 6 (the total number of projects). - The probability of success (p) is 0.6 (the probability that a project is completed on time). - The number of successes (k) we are interested in is 4 (the Show more…
Show all steps
Close
Your feedback will help us improve your experience
Hoan Nguyen and 94 other Intro Stats / AP Statistics educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Key Concepts
Recommended Videos
If 4 students are late everyday to class on average. What is the probability that on any given day, 6 students will be late.
Hoan N.
Company records show that of their all projects, 75% will not make a profit. a. What is the probability that of 6 randomly selected projects, 4 will make a profit. <2 marks> b. What is the probability that of 6 randomly selected projects, non will make a profit. <2 marks>
Megha S.
If 60% of loan applications are typically approved, what is the probability that at least 6 applications will be approved out of 10 loan applications received?
Nick J.
Recommended Textbooks
Elementary Statistics a Step by Step Approach
The Practice of Statistics for AP
Introductory Statistics
Transcript
18,000,000+
Students on Numerade
Trusted by students at 8,000+ universities
Watch the video solution with this free unlock.
EMAIL
PASSWORD