00:01
Hi, this is the given diagram or network node diagram.
00:04
In question a, we need to find out the matrix which is relevant to this diagram.
00:10
So let us draw that matrix.
00:13
So the matrix a for gilevan network diagram in the label cost is like this.
00:19
And the network tree look like this.
00:23
Now let us calculate the node cost.
00:26
So in this way we can calculate the node cost.
00:29
Let us start with p7.
00:30
So p7 minus p4 equal to c74 that is equal to 4.
00:36
Again p7 minus p6 equal to c76 that is equal to 1.
00:42
Now we use the formula that is c of ij equal to c of ij minus d of i minus p of j and over ij belongs to t.
00:59
Now we set negative node cost for c21 bar equal to c21 minus p2 minus p1 equal to 3 minus 1 plus 6 which is equal to minus 2...