Question

Prod 100 $130 / unit 90 units / week D 12 min C 10 min A 10 min B 5 min RM #1 $20/unit Prod 200 $125 / unit 80 units / week D 8 min B 5 min A 9 min RM #2 $20/unit Prod 300 $140/ unit 100 units/week C 7 min B 5 min RM #3 $20/unit C 8 min B 6 min RM #4 $20/unit RM #5 $20/unit D 6 min A 7 min RM #6 $10/unit A, B, C & D: 1 unit of each resource Availble time: 2,400 minutes / week Setup time: 20 minutes per machine per task Operating Expenses (not including RM): $11,000/week RM #7 $5/unit

          Prod 100
$130 / unit
90 units / week
D
12 min
C
10 min
A
10 min
B
5 min
RM #1
$20/unit
Prod 200
$125 / unit
80 units / week
D
8 min
B
5 min
A
9 min
RM #2
$20/unit
Prod 300
$140/ unit
100 units/week
C
7 min
B
5 min
RM #3
$20/unit
C
8 min
B
6 min
RM #4
$20/unit
RM #5
$20/unit
D
6 min
A
7 min
RM #6
$10/unit
A, B, C & D: 1 unit of each resource
Availble time: 2,400 minutes / week
Setup time: 20 minutes per machine per task
Operating Expenses
(not including RM): $11,000/week
RM #7
$5/unit
        
Show more…
Prod 100
130 / unit
90 units / week
D
12 min
C
10 min
A
10 min
B
5 min
RM #120/unit
Prod 200
125 / unit
80 units / week
D
8 min
B
5 min
A
9 min
RM #220/unit
Prod 300
140/ unit
100 units/week
C
7 min
B
5 min
RM #320/unit
C
8 min
B
6 min
RM #4
20/unit
RM #520/unit
D
6 min
A
7 min
RM #6
10/unit
A, B, C     D: 1 unit of each resource
Availble time: 2,400 minutes / week
Setup time: 20 minutes per machine per task
Operating Expenses
(not including RM):11,000/week
RM #7
5/unit

Added by Savannah N.

Close

Elementary Statistics a Step by Step Approach
Elementary Statistics a Step by Step Approach
Allan G. Bluman 9th Edition
AceChat toggle button
Close icon
Ace pointing down

Please give Ace some feedback

Your feedback will help us improve your experience

Thumb up icon Thumb down icon
Thanks for your feedback!
Profile picture
Theory of Constraints, please help and please show your work. Thank you!! Prod 100 Prod 200 Prod 300 $130/unit $125/unit 80 units/week $140/unit 90 units/week 10 units/week D D 8 min D 6 min 12 min RM#7 $5/unit B C 7 min 10 min 5 min 8 min A B A 9 min B 5 min B 6 min A 7 min 10 min 5 min RM RMS RM6 $20/unit $20/unit $20/unit $20/unit $20/unit $10/unit A, B, C & D - 1 unit of each resource Available time: 2,400 minutes/week Setup time: 20 minutes per machine per task Operating Expenses not including RM: $11,000/week
Close icon
Play audio
Feedback
Powered by NumerAI
Danielle Fairburn Kathleen Carty
Ivan Kochetkov verified

Madhur L and 59 other subject Intro Stats / AP Statistics educators are ready to help you.

Ask a new question

*

Labs

-

Want to see this concept in action?

NEW

Explore this concept interactively to see how it behaves as you change inputs.

View Labs

*

Key Concepts

-
Key Concept
Premium Feature
Explore the core concept behind this problem.
Play button
Key Concept
Premium Feature
Explore the core concept behind this problem.
Your browser does not support the video tag.

*

Recommended Videos

-
format-to-linear-programming-problem-a-company-manufactures-two-products-pand-pprofit-per-unit-for-pis-rs200-and-for-p-is-rs300three-raw-materials-mmand-m-are-requiredone-unit-of-pneeds-5-un-93903

A company manufactures two products P1 and P2. Profit per unit for P1 is Rs. 200 and for P2 is Rs. 300. Three raw materials M1, M2 and M3 are required. One unit of P1 needs 5 units of M1 and 10 units of M2. One unit of P2 needs 18 units of M2 and 10 units of M3. Availability is 50 units of M1, 90 units of M2 and 50 units of M3. Formulate as LPP. 8. A firm produces two products X and Y. Minimum 50 units of X should be produced. There is no limit for producing Y. Profit per unit is Rs. 100 for X and Rs. 150 for Y. Product Resource Requirement Resource Availability X 20 Machine Hours Machine Hours = 2500 10 Labour Hours Labour Hours = 3000 Y 10 Machine Hours 15 Labour Hours Formulate as LPP.

Madhur L.

items-number-of-hours-required-on-machines-m1-m2-m3-a-1-2-1-b-2-1-125-a-manufacturer-has-three-machines-m1-m2-and-m3-installed-in-her-factory-machine-m1-and-m2-are-capable-of-being-operated-10897

Items Number of hours required on Machines M1 M2 M3 A 1 2 1 B 2 1 1.25 A manufacturer has three machines M1, M2 and M3 installed in her factory. Machine M1 and M2 are capable of being operated for at most 12 hours, whereas machine M3 must be operated for at-least 5 hours a day. She produces only two items A and B each requiring the use the all three machines. The number of hours required for producing 1 using of each of A and B on three machines are given in the following table ABOVE: She makes profit of $600 and $400 on items A and B respectively. Write an LP formulation for maximizing the profit by selling items A and B. 1. Variables: 2. Objective (specify min or max): 3. Constraints:

Sri K.

consider-the-following-scenario-there-are-two-products-x-and-y-that-are-being-manufactured-as-a-part-of-the-process-both-x-and-y-need-to-be-processed-on-a-machine-which-has-100-hours-availab-00848

Consider the following scenario: There are two products X and Y that are being manufactured. As a part of the process, both X and Y need to be processed on a machine which has 100 hours available. Each product X and Y needs 2 hours for each unit. In an algebraic model, let X denote the number of units of product X manufactured, and Y denote the number of units of product Y manufactured. Which of the following constraints would fully specify this restriction in an optimization model? A) X ? 100 and Y ? 100 B) X + Y ? 100 C) 2X + 2Y ? 100 D) None of the above

Frank D.


*

Recommended Textbooks

-
Elementary Statistics a Step by Step Approach

Elementary Statistics a Step by Step Approach

Allan G. Bluman 9th Edition
achievement 1,528 solutions
The Practice of Statistics for AP

The Practice of Statistics for AP

Daren S. Starnes, Daniel S. Yates, David S. Moore 4th Edition
achievement 1,658 solutions
Introductory Statistics

Introductory Statistics

Barbara Illowsky, Susan Dean 1st Edition
achievement 1,908 solutions

*

Transcript

-
00:01 Hi, here for the given question we are given that a company manufactures 2 unit so let x1 be number of unit for p1 and x2 be number of unit for p2 so here the maximum profit for p1 is 200 and for p2 it is equal to 300 now there are 3 raw materials m1 m2 and m3 now further here in the question we are given that here there are 5 units of m1 for p1 further here we are given that we need 10 unit of m2 for p1 and whereas we need 18 unit of m2 for p2 and here we are given that we need 10 unit of m3 now further here we are given that m1 is greater than or equal to 50 m2 is greater than or equal to 90 and m3 is greater than or equal to 50 so here now using all the above condition here we have maximum of z is equal to 200 x1 plus 300 x2 whereas subject to constraint equation will be 5 x1 less than or equal to 50 10 x1 plus 18 x2 less than or equal to 90 and again we have 10 x2 less than or equal to 50 whereas x1 and x2 are greater than or equal to 0 so this is the lpb problem lpb formulation so solution of the first part now moving towards the second part of the question here in the second part we are given that here for x we need 20 machine hours and 10 labor hours…
Need help? Use Ace
Ace is your personal tutor. It breaks down any question with clear steps so you can learn.
Start Using Ace
Ace is your personal tutor for learning
Step-by-step explanations
Instant summaries
Summarize YouTube videos
Understand textbook images or PDFs
Study tools like quizzes and flashcards
Listen to your notes as a podcast
Continue solving this problem
Create a free account to:
  • View full step-by-step solution
  • Ask follow-up questions with Ace AI
  • Save progress and study later
Continue Free
Join the community

18,000,000+

Students on Numerade


Trusted by students at 8,000+ universities

Numerade

Get step-by-step video solution
from top educators

Continue with Clever
or



By creating an account, you agree to the Terms of Service and Privacy Policy
Already have an account? Log In

A free answer
just for you

Watch the video solution with this free unlock.

Numerade

Log in to watch this video
...and 100,000,000 more!


EMAIL

PASSWORD

OR
Continue with Clever