And so it wants you to, for the following data, calculate the number of workers required for the level of production and resulting in the month -end inventories.
00:13
Each worker can produce nine units per day.
00:16
And the desired inventory is 800 units.
00:21
Why is it not possible to reach the exact ending inventory target? so the first thing that you're going to do is calculate the total forecast demand for the six months.
00:29
So total forecast demand for six months.
00:38
So you're going to take the total demand equals the $2 ,800, that's month one, plus $3 ,000, which is month two, plus $2 ,700, which is month three, plus $3 ,300, which is month four, and $2 ,900, which is month five, plus $3 ,200, which is month six.
00:57
And that is going to be a total of 17 ,900 units.
01:04
Then you're going to calculate the total required production.
01:09
So the total required production is 17 ,900 plus 800 minus 1 ,000 and that's going to be 17 ,700 units.
01:30
Then you are going to calculate the total number of working days over the six months.
01:43
You are going to take 20 plus 24 plus 12 plus 22 plus 20 plus 19 and you're going to get 117 days.
01:55
Number four, you are going to calculate the daily leveled production...