XYZ company is preparing the MRP for the product A (structure try shown below):
A
B (5)
C (2)
D (2)
E (3)
Complete filling the MRP for items AB, and D, knowing that the following quantities are required: 30 A in day 7, 10 B spares in day 6.
Period Required LT=2 Order Placed Required B LT=3 Order Placed D Required LT=1 Order Placed
2
3
4
5
6 [g] [h] [z]
[a]
[b] [c]
[d] [e] [y]
[k] [x]
A