Years Marginal Benefit Marginal Cost
0 0 $300
1 $130 $0
2 $130 $0
3 $230 $10
The table above describes a project that has benefits and costs over time. If the interest rate (a.k.a. the discount rate) is 8%, what is the present value of net benefits?
Between -$100 and $0, inclusive
Less than -$100
Greater than $100
Between $1 and $100, inclusive