• Home
  • Textbooks
  • Integral Logistics Management: Operations and Supply Chain Management Within and Across Companies,
  • Cost Estimating, Job-Order Costing, and Activity-Based Costing

Integral Logistics Management: Operations and Supply Chain Management Within and Across Companies,

Paul Schönsleben, Steven R. Schmid, Bo O. Jacobson

Chapter 15

Cost Estimating, Job-Order Costing, and Activity-Based Costing - all with Video Answers

Educators


Chapter Questions

Problem 1

Job-Order Costing
Two products $\mathrm{A}$ and $\mathrm{B}$ are produced from material $\mathrm{Z}$ with a batch size of 40. Consumption is the same for each product: $50 \mathrm{~g}$ per product $\mathrm{A}$ or $\mathrm{B}$. The cost of $1 \mathrm{~kg}$ of material Z is $$\$ 20$$.

For the sake of simplicity and comparison in our example, the manufacturing process is the same for products $\mathrm{A}$ and $\mathrm{B}$ : two operations $(1$ and 2$)$ at two work centers (WCl and WC2). The standard time for each operation is 1 hour per 40 units. Assume that setup time is negligible.

To calculate the costs of the manufacturing process, it is important to take into account the costs of the two work centers WCl and WC2 in addition to the standard times. As Figure 15.7.1.1 shows, WCl is more machine intensive, while WC2 is more employee intensive. The investments will be depreciated in 5 years, assuming 1000 productive hours per year. Further, assume that these costs make up the full manufacturing costs.
(COLUMN CANT COPY)
Following the principle of job-order costing, determine the cost accumulation values for products A and B marked "?" in the tables in Figures 15.7 .1 .2 and 15.7 .1 .3 (compare Figure 15.2.2.1.)

Check back soon!

Problem 2

Activity-Based Costing

Think again about products A and B described above. After reading Section 15.1.4, you know that tooling costs make up a sizable proportion of the fixed costs. If the costs of the tools used for products A and B are different, this should be apparent in the cost accumulation. However, that can only be achieved if we view tool utilization as a process in its own right. Following the principle of $\mathrm{ABC}$ and the steps involved (see Section 15.4.2), the characteristic variables for this process are defined as follows:
- ABC process: tool utilization, or use.
- Process costs: the manufacturing or procurement costs of the tool.
- Activity cost driver: the number of units produced with the tool. Why? Usually, it is not the length of time that a tool is utilized that determines its wear, but rather production of a certain number of units of the product. A good example would be pressing tools.
- Process cost rate: process costs divided by the total quantity of product units that are produced using the tool until the tool is used up or worn out.

Figure 15.7.2.1 shows a breakdown of the fixed costs in machine costs and costs for tools and devices.
(COLUMN CANT COPY)
As in exercise 15.7.1 above, the investitures in machines will be depreciated in 5 years, whereby 1000 productive hours are assumed annually. It is further assumed that a tool can be used to manufacture 20,000 products A or B before it is used up or worn out, no matter whether it is an expensive or inexpensive tool.

Since one hour of capacity is utilized for 40 units of products A or B, 200,000 products can be manufactured in 5000 productive hours. This means that, in that period, 10 tools will be required.
In the following, assume also that the same number of units of products $\mathrm{A}$ and B is manufactured. In this case, work center 1 will use 10 tools ( $5 \mathrm{Tl}$ and 5 T2 tools), which represents an investment of $$\$ 100,000$$. Work center 2 uses 10 tools (5 T3 and 5 T4 tools), which represents an investment of $$\$ 50,000$$. The sum of fixed costs is thus the same as in exercise 5 above.

Determine the values marked "?" in the cost accumulation tables in Figures 15.7 .2 .2 and 15.7 .2 .3 below (compare Figure 15.2.2.1).
(COLUMNS CANT COPY)
To calculate the process cost of the tool, use the following:
- The process quantity or quantity per for the ABC process "tool use for operation 1 (or 2)" is 1 (one use per unit produced).
- The total (target) quantity is the number of units produced.
- The process variable, or activity cost driver, is the "use of the tool."
- The process cost rate (or cost per unit) is the cost of the tool divided by the number of units that can be produced until the tool is used up.
- The process costs (target) are the product of the total (target) quantity times the cost per unit.
(COLUMNS CANT COPY)

Check back soon!

Problem 3

Comparing Job-Order Costing and Activity-Based Costing
a. Why is the cost per unit produced in the conventional job order costing exercise 15.7.1 ($$\$4.75$$) exactly the mean of the costs per unit of the two products in the ABC exercise 15.7.2 ($$\$4.30 and \$5.20$$)?
b. What product pricing considerations would you take into account on the basis of the results when calculating manufacturing costs by $\mathrm{ABC}$ ?
c. Would a change of the batch size ( 40 in both exercises) imply different results? Is this generally the case in the world of practice? What assumption made in the problem description for the sake of simplicity led to the special case of the two exercises?

Check back soon!