STEP-BY-STEP ANSWER:
Step 1: Identify all contract-related costs and the total estimated cost for the project.
Step 2: Calculate the percentage of completion by dividing the costs incurred to date by the total estimated costs.
Step 3: Multiply the total contract revenue by the percentage of completion to determine the cumulative revenue to be recognized.
Step 4: Subtract any revenue that has already been recognized in previous periods.
Step 5: Record the current period’s revenue as the difference calculated in Step 4.
Final Answer: Revenue recognized in the current period equals the adjusted percentage-of-completion revenue, ensuring that revenue recognition is aligned with work progress.