Okay, so the first question, fill this in as we go.
00:40
First question is the final inspection, what does the total defect count? okay, so the total defect, so what that means is we need to add up all the pieces.
00:56
Okay, so i'm just going to label these up here so we can see them.
00:59
So we know the defect for this blem is 56, and then we have 45 and 23.
01:10
And 12 and 8 and 6.
01:15
Okay, so we're gonna add all those numbers together.
01:19
Okay, so if we add all these together, i'm just gonna show up by circling them.
01:22
So we're gonna add each of these numbers.
01:26
Those are the counts.
01:27
So if we take 56 plus 45, oops, plus 45 plus the screen's being finicky here.
01:40
56 plus 45 plus 25 plus 23.
01:43
23 plus 12.
01:58
So 150.
01:59
Okay.
02:00
So the sum of all these is 150 at our total count.
02:03
So that's part a.
02:05
And we do prediograms.
02:07
We use the cumulative frequency.
02:09
So you need to have your sum regardless anyways.
02:13
Okay.
02:13
Part b says verify the 30 % for scratch.
02:17
Okay.
02:18
So if we look at scratch, i'm going to take this and look at scratch.
02:23
Scratch is the second one here.
02:25
Okay.
02:25
So i'm going to label it up here.
02:26
It's a little easier to see.
02:29
So to verify the scratch, we know we need to have the 45 is the part, and 150 is the total.
02:40
If i take 45 divided by 150, i should get 30.
02:42
So i'm going off to the side to do this...