Determine the work done on the mass to move it 10 meters.(A) 2.5 J(B) 50 J(C) 125 J(D) 250 J(E) 1,250 J
Step 1
The work done on an object is given by the formula: \[ W = F \cdot d \] where \( W \) is the work done, \( F \) is the force applied, and \( d \) is the distance over which the force is applied. Show more…
Show all steps
Your feedback will help us improve your experience
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Key Concepts
Recommended Videos
Calculate the work done in moving a body of mass 50 kg through a height of 5 m. (g = 10m/s2) 250 J 2500 J 25 x 103 J 2.5 x 105 J
A variable force acts on a 2.0 -kilogram mass, displacing the mass 5.0 meters. The force and displacement are graphed above. Determine the work done on the mass by the variable force. (A) 5 $\mathrm{J}$ (B) 10 $\mathrm{J}$ (C) 15 $\mathrm{J}$ (D) 20 $\mathrm{J}$ (E) 30 $\mathrm{J}$
If a $2.0$-kilogram mass is raised $0.05$ meter vertically, the work done on the mass is approximately (A) $0.10 \mathrm{~J}$ (B) $0.98 \mathrm{~J}$ (C) $40 . \mathrm{J}$ (D) $100 \mathrm{~J}$