So this question tells us that we're going to try to make coat shirts and slacks.
00:06
All right.
00:07
So i'm just going to call them coats shirts and slacks.
00:11
And we have to cut them.
00:15
So there's cutting involved and they're sewing.
00:18
And then finally there is packaging.
00:20
All right.
00:21
And what we're doing for each of those is we're putting a certain amount of time into them.
00:25
So 20 minutes, 60 minutes and five minutes for the coat.
00:31
15, 30, and 12 for the shirts.
00:34
And then 10, 24, and 6 for the slack.
00:39
And then it tells us that in terms of the time, it's actually available, and i'll just write as time available for now, all right, that time, is 115 hours for cutting, 280 hours for sewing in 65 hours.
00:58
And it's important that we make that distinction, because these are all in minutes, okay, and these are an hour.
01:03
So it does make a difference.
01:04
We have to convert...