Network Planning
Figure 12.7.3.1 shows a scheduled network with incomplete data for 6 operations and a start operation (administration time).
(GRAPH CANT COPY)
Fig. 12.7.3.1 Scheduled network (for you to complete).
a. For each process, please fill in the earliest start date (ESD) and the latest start date (LSD) in the scheduled network. What is the critical path, that is, the path with the longest duration? What is its lead-time margin, that is the slack time?
b. The operation time for operation 6 has not yet been determined. What is the longest possible time for operation $6($ lead-time $\operatorname{margin}=$ zero $)$ ?