Queues as an Effect of Random Load Fluctuations (1)
Answer the following questions using the relevant formulas in queuing theory (refer to Figure 12.2.2.4):
a. How many parallel workstations are needed to have an expected wait time of less than 10 hours, if capacity utilization is 0.95 , the mean of the operation duration is 2 hours, and the coefficient of variation of the operation duration is 1 ?
b. The capacity is 10 hours. How much does the expected wait time increase if load rises from 4 to 8 hours?
c. How is the expected wait time affected when the coefficient of variation increases from 1 to 2 ?