Question
Recalculate the NPV of the project in Question 5.9 with the discount rates now varying between years: $\mathrm{Y} 1,9.2 \% ; \mathrm{Y} 2,10.5 \% ; \mathrm{Y} 3,11.7 \% ; \mathrm{Y} 4,8.62 \%$.
Step 1
PV Year 1 = $100,000 / (1 + 0.092)^1 = $91,743.12 PV Year 2 = $120,000 / (1 + 0.105)^2 = $98,654.71 PV Year 3 = $150,000 / (1 + 0.117)^3 = $113,214.85 PV Year 4 = $200,000 / (1 + 0.0862)^4 = $150,073.89 Show more…
Show all steps