00:06
Part a, we want to know what is c of 400.
00:16
It is the total cost of making 400 units.
00:25
As always, the total cost is the fixed cost plus the total variable cost.
00:35
For fixed cost, we understand that it's $10 ,000.
00:40
The total variable costs are given in that table, and we can estimate them pretty well.
00:49
So, assuming that the curve is actually a curve and that the table is just representative points, let's look at the quantity intervals.
01:02
When you're going from zero to 100, the average seems to be about $22 .50 per unit times 100 equals $2 ,250.
01:29
In the interval from 100 to 200, the average appears to be about $19 per unit times 100 is $1 ,900.
01:46
In the interval from 200 to 300, the average seems to be on the dot 20 per unit times 100 equals $2 ,000.
02:02
And then from 300 to 400, the average appears to be 25 per unit times 100 equals $2 ,500.
02:28
So the total variable costs are 6, 6, 650.
02:43
Let's verify that.
02:44
0, 5, 14, 16, 8...