00:01
Today we'll be solving problem four from chapter seven of principles and applications of microeconomics.
00:06
This question gives us a company consolidated national acme, inc.
00:11
And it also gives us the quantity produced and two variables for total cost, total cost one and total cost two.
00:17
I've copied those values here into an excel sheet.
00:20
And the first part of the question wants to know which one of these is the long run cost curve and which one of them is the short run cost curve.
00:27
And there's sort of three ways that we know this.
00:29
So first of all, the long -run cost is always less than the short -run cost at the same quantity.
00:36
So as you can see, total cost 1 is always less than total cost 2 at the same quantity.
00:42
So we know from that alone that total cost 1 is the long -run cost curve.
00:48
So we're going to go ahead and label them.
00:53
Total cost 1 is the long -run cost curve, and total cost 2 is the short -run cost curve.
00:57
However, there's also a few other ways to know.
01:00
So there's no fixed cost for the long run at the zero -with unit.
01:04
And we can see that here that at the zero -with unit, the long -run total cost curve doesn't have a fixed cost.
01:10
The third way that we can know this is if we look at the long -run average total cost curves and the short -run average total cost curves.
01:18
So in order to calculate that, we're going to do the long -run average total cost curve and the short -run average total cost curve by dividing the long run cost curve by the quantity and doing the same thing for the short run cost curve.
01:39
Now obviously at zero we don't have a average total cost curve, but we know that the long run average total cost curve is always going to be an envelope of the short run average total cost curve.
01:52
So if we go ahead and plot these, we can see that the long run average total cost curve in blue is an envelope of the short run average total cost curve.
02:05
Part b if the question would like us to use the short run total cost curve to calculate the total fixed cost, total variable cost, average fixed cost, average variable cost, and marginal cost for each quantity.
02:18
So we know that the cost at the zero with unit is going to be the fixed cost.
02:23
So our total fixed cost at the zero with unit is going to be 350.
02:27
And since this is a fixed cost through all of the quantities, this is going to be our fixed cost for 037.
02:33
In order to calculate the total variable cost, we want to, subtract the fixed cost from our short run total cost.
02:42
So at the zero with unit our variable cost is zero, but as we move this formula down, we can see that our variable cost is going to be the short run total cost minus the total fixed cost...