Question
The power company must generate $100 \mathrm{kW}$ to supply an industrial load with $94 \mathrm{kW}$ through a transmission line with $0.09-\Omega$ resistance. If the load power factor is 0.83 lagging, find the load voltage.
Step 1
This is given by $P_{\text{line}} = P_s - P_L$. Substituting the given values, we get \[P_{\text{line}} = 100 \, \text{kW} - 94 \, \text{kW} = 6 \, \text{kW}\] Show more…
Show all steps
Your feedback will help us improve your experience
Narayan Hari and 92 other educators are ready to help you.
Ask a new question
Labs
Want to see this concept in action?
Explore this concept interactively to see how it behaves as you change inputs.
Key Concepts
Recommended Videos
An industrial load that consumes $40 \mathrm{kW}$ is supplied by the power company, through a transmission line with $0.1-\Omega$ resistance, with $44 \mathrm{kW}$. If the voltage at the load is $240 \mathrm{V} \mathrm{rms}$, find the power factor at the load.
An industrial load is supplied through a transmission line that has a line impedance of $0.1+j 0.2 \Omega .$ The 60 -Hz line voltage at the load is $480\underline{/0^{\circ}}$ $\mathrm{V}$ rms. The load consumes 124 $\mathrm{kW}$ at 0.75 pf lagging. What value of capacitance when placed in parallel with the load will change the power factor to 0.9 lagging?
An industrial load consumes $100 \mathrm{kW}$ at 0.8 pf lagging. If an ammeter in the transmission line indicates that the load current is $200 \mathrm{A} \mathrm{rms}$, find the load voltage.
Transcript
Watch the video solution with this free unlock.
EMAIL
PASSWORD