1.
Calculate Project ABC's CUMULATIVE COST in April based on its time-phased budget
in Table 1.0 below. (Show your calculation).
(6 Marks)
January
February
March
April
May
Activity
(RM)
(RM)
(RM)
(RM)
(RM)
Survey
9,500
Design
4,800
2,750
Cleaning
2,000
2,500
1,750
Foundation
2,100
14,500
Framing
5,000
42,800
Plumbing
10,800
7,200
Wiring
Table 1.0