3. Moza Co. purchased land as a factory site for $1,350,000. Moza paid $120,000 to tear down
two buildings on the land. Salvage was sold for $8,100. Legal fees of $5,220 were paid for title
investigation and making the purchase. Architect's fees were $46,800. Title insurance cost
$3,600, and liability insurance during construction cost $3,950. Excavation cost $15,670. The
contractor was paid $4,200,000. An assessment made by the city for pavement was $9,700.
Interest costs during construction were $255,000. The cost of the building that should be recorded
by Moza Co. is