Given the following project network, baseline, and the status information:
4.1. Using the percent complete (proportionality) rule to calculate Earned Value, develop a status
report for the end of period 4 by
a) Completing a table with the EV, AC, PV, CV, SV, SPI, and the CPI.
b) Based on your data, what is the status of the project?
c) Then, calculate how much money is needed to complete the remaining tasks (ETC), the total
cost forecast of the project (EAC) and variance at completion (VAC).
d) What is the forecast of the project at completion?
Status information - end of period 4:
Activity A: 100% complete. Actual cost: $200
Activity B: 60% complete. Actual cost: $100
Activity C: 50% complete. Actual cost: $200
4.2. Use the 50-50 rule to calculate Earned Value and develop a status report for the end of period
4 and complete the variances and performance indexes table. Calculate the EAC, and VAC.
Compared with the previous results, are there activities with a different EV?