Question 16 (1 point)
An X bar and R chart was prepared for an operation using 25 samples with seven
pieces in each sample. X double bar was found to be 24.8 and R bar was 5.50. During
production, a sample of seven was taken and the pieces measured 25, 32, 35, 28, 27,
24, and 26. At the time this sample was taken:
Only the range was outside the control limits.
Only the average was outside the control limits.
Both the average and range were within the control limits.