Question 21
Based on the table below, draw a network diagram in a separate paper. Using the critical path method, select the option that indicates the total duration
of the project (number of days that will take to complete the entire project):
\* 24 days
\* 20 days
\* 18 days
\* 22 days
Activity Duration [days] Predecessor(s)
A 5 -
B 2 -
C 3 A, B
D 5 -
E 6 -
F 4 D, E
G 2 C, F
H 5 G
I 10 G
J 3 H