5. Given the following network for a stock repurchase project
with outside consulting resource demands, construct a mod-
ified Gantt AOA chart with resources and a resource load
diagram. Suggest how to level the outside consulting load if
you can split operations.
code:
activity, time
resource units
a, 10
d, 10
2
6
2
b, 10
e, 5
1
4
3
10
f, 15
4
c, 5
8
4
g, 10
6
5
h, 5
i, 5
2
7