Calculator
At the beginning of the year, Hallett Company estimated the following Cutting Department Sewing Department Overhead Total $242,000 $350,000 Direct labor hours $592,000 31,200 100,000 Machine hours 131,200 150,000 150,000 Assume that Hallett has decided to use a plantwide overhead rate based on direct labor hours. Actual data for the month of June are as follows: Cutting Department Overhead Sewing Department Total $20,610 Direct labor hours $35,750 $56,360 2,800 Machine hours 8,600 11,400 13,640 Required: 13,640 per direct labor hour rounded to the nearest cent in your calculations, and round your final answer to the nearest dollar
3. Calculate the overhead rate for the Cutting Department and the Sewing Department using the plantwide overhead rate method. Round your answers to the nearest cent.