A project that provides annual cash flows of $15,300 for nine years costs $74,000 today.
NPV for project if required return is 8 percent = $21,577.49
NPV if the required return is 20 percent = $-12,326.21
Q. At what discount rate would you be indifferent between accepting the project and rejecting it? (enter your answer as a percent rounded 2 decimal places)