An IT project requires 6 activities. The table below displays
the expected time and budgeted cost for each activity.
Activity
Expected time (weeks)
Budgeted Cost
Immediate Predecessors
A
3
$2,000
None
B
4
$6,000
None
C
2
$7,000
A
D
5
$9,000
B
E
3
$3,000
C
F
6
$8,000
B,D
Develop a budget for the 15 weeks of the project using LS
times.