11.1 Develop a budget for the project described in Table 11.11, assuming that the cost of each activity is linearly distributed over its duration.
TABLE 11.11
Activity Duration (days) Immediate predecessors Cost
A 3 - $3,000
B 4 - 2,000
C 3 - 6,000
D 2 C 2,000
E 1 B 1,000
F 5 A 10,000
G 2 B 4,000
H 3 B 9,000
I 11 C 11,000
J 3 D, E 3,000
K 1 F, G 1,000
L 4 K 2,000
M 4 J, H 8,000