answer the three question in picture
Question 1. Determine the critical path associated with the following project network diagram a.0 b.1 ACF c. 2 a. d.3 b. ADG c. BEG d. There is no critical path C
Question 2. How many days can task B be delayed without delaying completion of the project?
D 7
A
G
3
5
B
10
F
E
11
Question 3. In the project network diagram below, given the estimated task times below, what is the approximate probability that the project will be completed within 25 days? (You will need to use the probability tables for this question, you should use a 99% confidence level) m Average A 6 7 14 10 12 10 c 2 3 3 D 7 7 E 5 5.5 9 6
D
F
7
10
6 3
6
H
25