Problem 4: A project consists of seven activities with the time estimates as follows:
a) Construct the PERT/CPM network for this problem. You should draw the network on paper, take a picture, and paste it into sheet 4. All calculation must be done on Excel for verification. (1 point)
b) What is the expected project completion time? What is the critical path? (0.5 point)
c) What is the probability that the project can be completed within 30 days? (0.5 point)