Consider the following regarding learning curves:
I. The mathematical relationship between time to perform a task and experience is generally linear.
II. A learning rate of 85% is superior to a learning rate of 80%.
III. The value of n is always negative for learning to occur.
IV. The value for k can be read directly from the Excel regression output (i.e. no transformation is needed).
Choose the correct response below:
Group of answer choices
Items I and IV are false; items II and III are true.
Items I, II, and IV are false; item III is true.
Items III and IV are false; items I and II are true.
Items II, III, and IV are false; item I is true.
All of the statements are true.
Given the following Excel output:
SUMMARY OUTPUT
Regression Statistics
Multiple R
0.989636184
R Square
0.979379777
Adjusted R Square
0.97680225
Standard Error
0.026005069
Observations
10
ANOVA
df
SS
Regression
1
0.256958976
Residual
8
0.005410109
Total
9
0.262369085
Coefficients
Standard Error
Intercept
4.634586597
0.019663831
X Variable 1
-0.23051146
0.011825476
Which of the following equations represents the best estimate of the learning process based on the regression output?
Group of answer choices
Yx = 4.63x - 0.2305
Yx = 100x - 0.2305
Yx = 102.98x - 0.2305
Yx = 102.98x^0.979
None of the above.
Which of the following statements is false?
Group of answer choices
If possible, you should always use regression to estimate k and n.
Organizations do not experience learning, only people do.
If a process is undergoing learning at an 80% rate, the first 10 units processed will require more time in total than the next 10 units processed.
A 70% learning rate is superior to a 90% learning rate.
Learning typically follows a pattern of exponential decay.
Which of the following statements is true?
Group of answer choices
In order to estimate k and n from raw data, we must have at least one "doubled pair."
Positive values for n indicate that we are experiencing "unlearning" (we are getting worse over time).
Exponential decay means that the improvement from the 10th unit to the 11th unit is less than the improvement from the 20th unit to the 21st unit.
All of the above statements are true.
All of the above statements are false.
Acme Widgets had an order to process 250 widgets. The first unit required 200 minutes to assemble. Before starting, the company estimated the amount of time it would require to assemble all 250 widgets if they learned at an 85% rate. After assembling all 250 widgets, Acme realized they had learned at an 80% rate. How much time less than their estimate did Acme take? You should be able to compute the answer within plus or minus 2 hours.
Group of answer choices
296.1 hours
126.6 hours
140.3 hours
91.2 hours
155.8 hours
If the 13th unit processed requires 87.00 minutes and the 26th unit requires 64.00 minutes, how much time would you estimate the 50th unit requires? (round to nearest whole number)
Group of answer choices
35 minutes
48 minutes
18 minutes
55 minutes
40 minutes
A process is learning at a 92% rate. The first unit required 70 minutes. How many units must be processed before the company cuts the processing time to 28 minutes?
Group of answer choices
Between 2,000 and 2,100 units
Between 2,500 and 2,600 units
Between 1,700 and 1,800 units
Between 1,000 and 1,100 units
None of the above is correct.
SUMMARY OUTPUT
Regression Statistics
Multiple R
0.993377
R Square
0.986799
Adjusted R Square
0.986359
Standard Error
0.022819
Observations
32
ANOVA
df
SS
MS
F
Significance F
Regression
1
1.167639
1.167639
2242.497
9.37E-30
Residual
30
0.015621
0.000521
Total
31
1.183259
Coefficients
Standard Error
t Stat
P-value
Lower 95%
Upper 95%
Lower 95.0%
Upper 95.0%
Intercept
3.92966
0.012854
305.7158
5.69E-54
3.903409
3.955911
3.903409
3.955911
X Variable 1
-0.22676
0.004789
-47.355
9.37E-30
-0.23654
-0.21698
-0.23654
-0.21698
Above is a regression analysis of data from a process that is undergoing learning. The initial raw data was entered in minutes. Predict how many minutes the 95th unit will require.
Group of answer choices
16.7
22.8
18.1
19.7
None of the above is accurate within 0.3 minutes.
Spaceley's Sprockets has just developed a new product. George Jetson, the Head of Product Development, feels that the product is a winner, but he also feels it would be an even better product if waited six more months for further development before launching. Unfortunately, Spaceley's closest competitor, Cogsley's Cogs, has a similar product in the development pipeline. George feels that if he launches the product now to get a head start on Cogsley, he has a 50% chance of achieving a high level of sales, a 30% chance of a medium level of sales, and a 20% chance of a low level of sales. If he waits, he has a 30% chance of a high level of sales and a 70% chance of a medium level of sales, with no chance of a low level of sales. High sales represent 100,000 units, medium sales represent 65,000 units, and low sales represent 10,000 units. If his objective is to maximize his expected number of units sold, what should George do and how many units would he be expected to sell?
Group of answer choices
Delay six months, 75,500 units
Delay six months, 71,500 units
Launch now, 71,500 units
Launch now, 62,000 units
None of the above is correct.
Which of the following statements is true with regard to best operating level?
Group of answer choices
In underutilization, the average unit cost of output increases.
In overutilization, the average unit cost of output increases.
The best operating level is the minimum average unit cost of output.
The best operating level is the denominator of capacity utilization calculations.
All of the above statements are true.