Using finite capacity scheduling, draw a Gantt chart for the schedule. (Marks 0.5)
How much machine idle time is there? (Marks 0.5)
How much idle time (waiting time) is there for each job? (Marks 0.5)
When is each job delivered? (Marks 0.5)
Which department is the bottleneck? (Marks 0.5)
Calculate the machine utilization? (Marks 0.5)
Question 1:
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
Job Work Center/Machine Hours Due Date (days)
1 A/3, B/2, C/2 3
2 C/2, A/4 2
3 B/6, A/1, C/3 4
4 C/4, A/1, B/2 3