Question 1:
Sequence the jobs shown below by using a Gantt chart. Assume that the
move time between machines is one hour. Sequence the jobs in priority
order 1, 2, 3, 4.
Job Work Center/Machine Hours
Due Date (days)
1
A/3, B/2, C/2
3
2
C/2, A/4
2
3
B/6, A/1, C/3
4
4
C/4, A/1, B/2
3