A project schedule has the following characteristics as shown in Table:
Activity | 1-2 | 1-3 | 2-4 | 3-4 | 3-5 | 4-9 | 5-6 | 5-7 | 6-8 | 7-8 | 8-10 | 9-10 |
Name | A | B | C | D | E | F | G | H | I | J | K | L |
Time (days)| 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
i. Construct PERT network
ii. Compute TE and TL for each activity.
iii. Find the critical path.