If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have?
Question 49 Select one:
a.
0.5 hours
b.
1.5 hours
c.
2.5 hours
d.
8.5 hours