00:03
In this question we talk about the lopez company.
00:06
This company uses both standard and budgets.
00:09
For the year, estimated production of product x is 500 ,000 units.
00:15
Total estimated cost for materials and labor is 1 .4 million and 1 .7 million.
00:20
Compute the estimates for a standard cost and b the budgeted cost.
00:25
We're being asked to round to 2dp.
00:28
Okay.
00:29
We're also being asked to find the materials, labor, standard cost and budgeted cost.
00:33
So we'll start with part a, which is the standard cost.
00:38
Now in order to calculate the standard cost, we have to do the total estimated cost of labour divided by the estimated production.
00:47
So standard cost, i'll just list this as sc for standard cost and abbreviation.
00:57
So we can start by finding out the total cost of labour.
01:00
Total cost of labor given to us is $1 .7 million...