00:01
Hello students, here is a question.
00:02
You have determined the profitability of a plant project by finding the present value of all the cash flow from the project.
00:08
Which of the following would case the project to look more appeal in terms of the present value of those cash flows? so, this is our question.
00:16
Let us discuss the answer further.
00:17
So, here we have an options given in the question.
00:20
The first option says that the discount rate discount rate decreases.
00:26
The discount rate decreases and the second option says that the cash flow are extended over extended over a long period of time, a long period of time, but the total amount of but the total amount of cash flow remains same and option c is the discount rate increases.
01:09
The discount rate increases and option d is answer a and b above are the correct answers are a and b of above.
01:26
So, these are the options we have.
01:28
Let us discuss this.
01:29
So, first we need to understand that the present value of a cash flow is calculated by the discounting future cash flow to their present value using the discount rate.
01:37
So, the higher the discount rate, the lower the present value of a cash flow.
01:41
So, now let us look the options.
01:43
So, option a is the discount rate decreases...