Problem 1:
Perform unit commitment for this three-generator system considering the first three hours only. Ignore reserve requirement and jumping constraints.
Problem 2:
Perform unit commitment for this three-generator system considering the first three hours only. Enforce linear constraints. However, take into consideration that the reserve requirement at each hour is at least 79% of the load of that hour. What do you observe?
Problem 3:
Perform unit commitment for this three-generator system considering the first three hours only. Ignore reserve requirements. However, take into consideration that the ramp rate for all units is 55 MW/min. What do you observe?
Problem 4:
Perform unit commitment for this three-generator system considering all five hours. Ignore reserve requirements and ramping constraints.
Hint: You might need to define the state not only by the unit status, but also by the unit history. For example, consider the combination 011 (unit 1 OFF, unit 2 ON, unit 3 ON). On the slides, this represented one state. In general, however, at least two states should be defined by 011: a state where unit 2 has been ON for one hour only, and a state where unit 3 has been ON for two hours.